Dinah’s Hollow Project Latest
Published: 06 November 2026
Dinah’s Hollow Project Stakeholder Update – September 2026
Works Update
The main bank stabilisation work in the Hollow is substantially complete, with all soil nails in place and the mesh system installed. The final tensioning of the mesh is currently being completed. Drainage work through in the Hollow is ongoing and progressing through the site, with kerbing work following behind this. The shuttle signal reinstallation has started and will continue into October. The signal equipment has been in storage during the work and will be reconfigured and tested as part of their installation. Other works in October include starting the shotcrete walling, the start of surfacing works and installing bat and bird boxes. All construction work is currently on track to be finished in December and to have the C13 reopen by the end of the year, as planned. Further completion and reinstatement works may be required in the New Year, but these will be carried out ‘offline’ and with the road open.
C13 / Melbury Abbas Temporary Traffic Arrangements
The C13 closure and temporary traffic management measures in Melbury Abbas village are all booked to the end of the year. These measures will only be removed when construction is complete and the compound has been removed. The National Trust may need to close Spread Eagle Hill next month for tree works. They will be responsible for organising the necessary traffic management and any letters/publicity. The works will be carried out off-peak.
A350 Signage, Speed Limits & Temporary Signals
The review of the temporary 20mph speed limits along the A350 has taken longer than anticipated. We’re continuing to process our data while awaiting a report back from Dorset Police following their proactive policing of the temporary speed limits. These reports will form the basis of an evidence-based approach to thoroughly reviewing the temporary 20mph restrictions on the A350.
Iwerne Minster signals
Given the level of public interest and the petition submitted, the two-way temporary traffic signals at Iwerne Minster have been reviewed. The decision, made by senior officers with agreement from Cabinet Member for Place Services, is that the signals remain in place for the duration of the Dinah's Hollow works: The project team remain of the view that the temporary traffic signals continue to provide appropriate and proportionate means of managing traffic through Iwerne Minster during the Dinah's Hollow diversion. Initial reviews of CCTV survey information and available traffic data indicate that the signals are facilitating a balanced flow of traffic through the existing priority give and take restriction and are not resulting in a material increase in overall journey times or queue lengths when considered alongside the wider impacts of diversion traffic. The original risk assessment identified several potential risks associated with increased traffic volumes on the diversion route, including traffic queueing at the priority narrowing, driver conflict, pedestrian movements associated with Clayesmore School and increased traffic activity at the Tower Hill junction. Officers consider that the temporary traffic signals continue to assist in managing these risks by regulating traffic movements through the restricted section of highway, providing predictable gaps within traffic flows and supporting safer opportunities for pedestrian crossing movements. Officers acknowledge the concerns raised through the petition process and by some residents regarding congestion, delays, rat running, junction visibility and the wider impacts on the local community. These concerns have been carefully considered alongside feedback received from other stakeholders, including Clayesmore School and Iwerne Minster Parish Council, who have highlighted the perceived benefits of the current arrangement in relation to pedestrian safety and traffic management. Having reviewed the available evidence and stakeholder representations, officers remain satisfied that the temporary traffic signals represent the most appropriate traffic management arrangement for the duration of the Dinah's Hollow diversion and continue to address the risks identified within the original assessment.
Temporary lights stuck on red
Our traffic management operations regularly change the batteries on the lights and continue to attend whenever lights are reported as being stuck on red. No faults have been found with the lights and we believe this has been caused by vehicles squeezing onto the end of a green run and running the red light. As the lights are vehicle activated, the system will try to reset if it registers conflicting movements and thinks there is a queue between the two signal heads that needs to be cleared – providing a small amount of ‘all red’ to facilitate this.
Public Notice 13th July 2026
Download the full pdf here

Dinahs Hollow A350 TM Meeting 3rd June 2026
Download the pdf here
Dinah’s Hollow Project – Stakeholder Update (April 2026)
Works Update Soil nailing is about to start. This follows reprofiling of the slope and final hand scaling to remove ridges. Specialist engineers also attended site to finalise arrangements. The soil nailing will start slowly with trial nails and testing before getting fully underway. Our main phase of vegetation and tree clearance has been completed. All our ecological work is being carried out under the agreed licence conditions and under strict supervision by the professionally accredited licenced ecologists who are accountable to Natural England.
See full report here
Dinah’s Hollow Project – Stakeholder Update (March 2026)
Summary
Since the February update, the project has moved from a largely preparatory phase into active delivery. Drainage works are now progressing well, with further elements such as fencing, haul road construction and soil nailing about to begin. The March update places greater emphasis on site safety, including concerns around unauthorised access, and provides reassurance on recent issues such as water pollution (with no concerns identified by the Environment Agency) and a quickly resolved utility strike. Traffic management updates are more focused on compliance and enforcement, alongside planned communications to address unsafe driving. In contrast to February’s more detailed and explanatory approach, the latest update reflects implementation on the ground, with confirmed measures such as 20mph limits and bollard installation now in place.
Progress of Works
Drainage operations are now advancing at a good pace following an improvement in weather conditions.
Additional vegetation clearance is scheduled to commence in April. Prior to this, ecological surveys will be carried out to check for the presence of bats and dormice. In accordance with the Natural England licence, further clearance will only proceed once it has been confirmed that any protected species have safely relocated.
Fencing installation and the creation of a haul road are expected to begin shortly.
Soil nailing works are planned to start next month. These activities are not anticipated to cause significant disturbance to nearby residents; however, acoustic monitoring will be undertaken on site as a precaution.
Concerns raised locally regarding potential water pollution have been investigated by the Environment Agency, which has confirmed that no issues have been identified.
On Monday 16 March, a BT fibre optic cable was inadvertently damaged. Repairs were completed the same day and internet services were promptly restored.
Site Safety
Construction safety remains a top priority. There have been several instances of unauthorised access through the designated works area, which is a cause for concern.
All fenced-off areas are strictly for construction use and must not be entered by the public.
All personnel working on site have completed a safety induction and are required to wear appropriate Personal Protective Equipment (PPE), including high-visibility clothing, hard hats and steel toe-capped boots. In addition, all workers hold valid Construction Skills Certification Scheme (CSCS) cards, demonstrating their training, qualifications and understanding of health and safety requirements.
From April, the main phase of construction will begin, involving larger machinery and increased site activity. For safety reasons, the public is strongly advised to keep out of all restricted areas.
C13 / Melbury Abbas Temporary Traffic Management
There continue to be reports of some motorists, believed to be repeat offenders, disregarding the one-way system. Enforcement of this measure falls under police responsibility, as site staff do not have legal authority to intervene.
To help address ongoing issues such as rat-running and unsafe driving, targeted messaging was shared via council social media channels over the Easter holiday period.
A350 Signage, Speed Restrictions and Temporary Signals
A temporary 20mph speed limit has now been introduced on several side roads connecting to the A350. This has reduced the amount of signage at junctions and improved visibility for road users.
Additionally, bollards have been installed along Mill Street to prevent vehicles from mounting and damaging the verge.
I am aware of a growing number of residents who question the efficacy of the 20mph and traffic lights along the route and I shall be discussing this with officers at our next meeting in April. It is important to find a balance between safety and overreach!